Back to Business as Usual in 10 days

Installation of an attack resistant enhanced shop-front to a previously damaged Petrol Forecourt

Challenge

To refit a PFS shop-front to withstand attack, in a very tight timeframe to enable them to continue trading.

Solution

Having previously built a relationship with this client while enhancing their petrol forecourt doors to withstand attack and delay entrance to their PFS sites, they approached us with confidence that we would be able to quickly and effectively provide a solution.

A PFS site had been rammed causing significant damage, compromising the store, and forcing them to close. Within two days of the incident we were able to conduct a site survey, allowing us to manufacture and install the enhanced shop-front with additional security specifications in the following 8 days.